Marrakech Airport Expansion Reaches 15% as Capacity Targets Diverge
Marrakech-Menara Airport’s terminal expansion was 15 per cent complete at the end of September, according to the latest progress figure presented to Parliament. The number is a useful marker on a project often described in future-tense superlatives: the enlarged terminal is under construction, not open.
Transport Minister Abdessamad Kayouh put the figure before the House of Representatives’ infrastructure committee on 3 November, in a presentation on the ministry’s 2027 budget. He placed the Marrakech programme at 3 billion dirhams and said it was intended to double annual capacity from eight million passengers to 16 million by 2028.
The physical programme is larger than a single new hall. ONDA’s project page describes an extension of the existing terminal complex, with changes to passenger processing, baggage systems, security, boarding areas, aircraft stands and landside access. Work is therefore proceeding around an airport that remains in daily operation.
The capacity target, however, is not yet consistent across current institutional material. Kayouh’s latest figure is 16 million passengers a year by 2028. An African Development Bank financing announcement dated 30 September gives Marrakech a target of 14 million by 2030, while ONDA’s own project page still states 11.5 million. Those figures may reflect different phases or scopes, but they should not be flattened into one supposedly settled number; 16 million is the latest ministerial target, not the airport’s present certified capacity.
No public opening date for a completed new terminal section was supplied in the material reviewed. The practical fact for now is construction progress: 15 per cent at the end of September, with the overall programme still scheduled against a 2028 horizon.
The same parliamentary presentation repeated a separate plan for a future high-speed rail journey of under 55 minutes between Mohammed V Airport and central Marrakech. That proposal depends on Casablanca airport’s new rail-linked terminal and the wider high-speed network; it is not a service available today, nor a substitute for the Marrakech airport works already under way.
Cover: the existing Marrakech-Menara terminal, photographed before the latest expansion is complete; file image via Yabiladi.